Schedule for our project

Schedule becoming clearer

A letter from the Council has arrived. It sheds light on how we can move forward with our housing development in concert with the drainage works that Council would like to do on our block.

Read More
Discussion with Engineering

Discussion with Engineering

A meeting with Council Engineering was another positive experience. They are enthusiastic about going ahead with the modified storm drainage project based on a third easement on our property. If we formally agree to this arrangement, it is possible the work could be completed within a 6 month time frame.

Read More
Make a plan for our house development

Make a plan

With a positive response from Council, it's time to create a plan showing the major activities and when we would like to have those activities completed.

Read More

Indigenous garden ideas

Latest news on discussions with Council. Wheels are turning in the background with regards to the clarifying the link between our planning permit and Engineering’s idea to run a third easement ...

Read More

Responding to the surprise

Responding to the surprise about the potential impact of Council drainage works on our project timeline has taken a few days.  It took some time to process the feedback and work ...

Read More

Spanner in the works

You know that bit in Grand Designs when Kevin McCloud turns to the camera and says, “Building a house doesn’t always go smoothly as we are about to find out ...

Read More